Brooklyn H.
08/06/2020 12:00:00 SA
I own a 110 year-old house in Brooklyn. I have lived here for 33 years.
Our clay sewer pipes are as old as the house and we were tired of late night sewer clog emergencies. So, after 33 years of procrastination, we decided to do the big-dig and have our main sewer line replaced.
In Brooklyn, I found two companies that specialize in Sewer Main replacement I selected Main Man Water Works because they had a higher yelp rating than the other company and my next door neighbor had good results when they used Main Man Water Works to replace their sewer main. We called Scott, Main Man's master plumber, scheduled an estimate the same week, and started the work by the following week.
The sewer main replacement took two days, from start to finish. They were able to tunnel under our front steps and front porch so both survived the ordeal undamaged. (Hip, hip hurray!!) The new sewer line was installed and working on the first day. On the second day, the job was finished, including hooking up an active storm drain into the sewer line (somehow skipped on the first day), replacing the cement walkway, and replacing a small section of cement floor that had to be removed in the basement near the pipe traps.
For the main job, the installation of the sewer-main, they know their stuff inside-and-out, and that part was worry-free. The second day was also ok, but we had to ask them correct a few of the finishing details.
For clarity, here are the finishing details we had ask them to correct. We had to ask them to spend more time tamping (packing down) the filled soil. Extra tamping takes more time & delays pouring the cement walkway, but reduces the risk of a sinking, sagging walkway in a few years. When pouring the cement, they initially left out the expansion joints and we had to ask them to add expansion joints (heavy felt strips) in the cement in order to reduce risk of future cracking. Finally, when restoring the pit for the sewer trap, they were initially going to make the pit twice as large. At our request, they moved the wood backer-boards before pouring the cement and restored the pit to approximately the original size.
In summary, their work is very good, but be prepared to oversee and correct some of the finishing details near the end of the job.